SMART360 v2 Automation Project - Management Plan
1. Management
1.1 Project Profiling
Project Name: SMART360 v2 Test Automation Suite Development
Project Duration: 12 weeks (Starting August 11, 2025 - Ending November 2, 2025)
Team Size: 5 automation engineers
Target System: 74 stories across 6 modules (CX, CX-Web, MX, Onboarding, BX, WX, Communication)
Project Objectives:
- Develop comprehensive automation framework using Playwright + pytest
- Achieve 95% API coverage and 85% UI coverage
- Implement CI/CD integration with <4 hour execution time
- Establish sustainable maintenance procedures
1.2 Scope of the Project
In Scope:
- API Automation for all 6 modules (74 stories)
- UI Automation for critical user journeys
- End-to-End testing scenarios
- CI/CD pipeline integration
- Test data management framework
- Performance and cross-browser testing
- Documentation and knowledge transfer
Out of Scope:
- Production environment testing (smoke tests only)
- Manual test case creation
- Performance load testing beyond validation
- Security penetration testing
- Mobile app automation
Module Priority Distribution:
- High Priority: CX + CX-Web (26 stories), MX (14 stories), Onboarding (15 stories)
- Medium Priority: BX (8 stories), WX (5 stories), Communication (6 stories)
1.3 Milestone Delivery and Timeline
Phase 1: Foundation & Framework (Weeks 1-3: Aug 11 - Aug 31, 2025)
- Week 1 End (Aug 17): Project structure and environment setup complete
- Week 2 End (Aug 24): Core framework architecture delivered
- Week 3 End (Aug 31): Framework validation and team training complete
Phase 2: API Automation (Weeks 4-6: Sep 1 - Sep 21, 2025)
- Week 4 End (Sep 7): CX + MX API automation (70% critical APIs)
- Week 5 End (Sep 14): Onboarding + remaining module APIs complete
- Week 6 End (Sep 21): Full API regression suite operational (95% coverage)
Phase 3: UI Automation (Weeks 7-9: Sep 22 - Oct 12, 2025)
- Week 7 End (Sep 28): Core UI framework and critical journeys
- Week 8 End (Oct 5): Primary module UI automation complete
- Week 9 End (Oct 12): Secondary modules and cross-browser testing complete
Phase 4: Integration & Deployment (Weeks 10-12: Oct 13 - Nov 2, 2025)
- Week 10 End (Oct 19): End-to-End scenarios and integration testing
- Week 11 End (Oct 26): CI/CD pipeline setup and optimization
- Week 12 End (Nov 2): Documentation, knowledge transfer, and go-live
1.4 Check-in Dates and Communication Protocol
Stakeholder Audience:
- Primary: Product Owners, Development Team Leads
- Secondary: QA Managers, DevOps Team, Project Management
Communication Schedule:
Weekly Check-ins (Fridays 3:00 PM):
- Audience: Development Team Leads, QA Manager
- Format: 30-minute status meeting
- Pre-check-in: Status report sent Thursday EOD
- Content: Progress, blockers, next week priorities
Bi-weekly Executive Updates (Fridays 4:00 PM - Weeks 2, 4, 6, 8, 10, 12):
- Audience: Product Owners, Stakeholders
- Format: 45-minute presentation + dashboard review
- Pre-check-in: Executive summary sent Wednesday
- Content: Milestone progress, risk status, timeline updates
Phase Gate Reviews:
- Phase 1 Review: September 2, 2025 (Go/No-go for API development)
- Phase 2 Review: September 23, 2025 (Go/No-go for UI development)
- Phase 3 Review: October 14, 2025 (Go/No-go for deployment)
- Final Review: November 4, 2025 (Project closure and lessons learned)
Risk Escalation Procedures:
Level 1 - Team Lead (Sarvesh):
- Daily blockers and technical issues
- Resource allocation within team
- Timeline adjustments <1 week
Level 2 - QA Manager:
- Cross-team dependencies
- Environment and infrastructure issues
- Timeline adjustments 1-2 weeks
- Budget and resource requests
Level 3 - Product Owner/Stakeholder:
- Scope changes
- Timeline adjustments >2 weeks
- Critical path risks
- Go/No-go decisions
Escalation Timeline:
- Immediate: Critical production issues or complete blockers
- 24 hours: Resource conflicts or major technical challenges
- 48 hours: Timeline risks or scope change requests
2. Project Team

2.1 Activities
Critical Phase 1: Foundation & Framework (Weeks 1-3)
Week 1 Activities (Aug 11-17, 2025):
- All Team: Environment setup and access validation
- Hetal (Lead): Project structure design and team role assignment
- Sarvesh: CI/CD pipeline research and tool evaluation
- GD: Pre-production environment stability assessment
- Jay: Development environment configuration
- Prachi: Documentation template creation
Week 2 Activities (Aug 18-24, 2025):
- Hetal: Core framework architecture implementation
- Sarvesh: Base API testing utilities development
- Jay: Page Object Model foundation
- GD: Test data management framework
- Prachi: Logging and reporting setup
Week 3 Activities (Aug 25-31, 2025):
- All Team: Framework validation and proof-of-concept testing
- Hetal: Team training sessions on framework usage
- Sarvesh: API framework validation
- Jay: UI framework validation
- GD: Performance testing foundation
- Prachi: Cross-browser testing setup
Phase 2: API Automation (Weeks 4-6)
Week 4 Activities (Feb 3-9, 2025):
- Hetal: CX + CX-Web API automation (26 stories)
- Sarvesh: MX API automation (14 stories)
- GD: Onboarding API automation start (15 stories)
- Jay: API test utilities and framework support
- Prachi: Communication API automation (6 stories)
Week 5-6 Activities (Feb 10-23, 2025):
- GD: Complete Onboarding + WX API automation (20 stories)
- Sarvesh: BX API automation (8 stories)
- All Team: API integration testing and regression suite setup
Phase 3: UI Automation (Weeks 7-9)
Week 7-8 Activities (Feb 24 - Mar 9, 2025):
- Hetal: CX + CX-Web UI automation (critical workflows)
- Jay: MX + Onboarding UI automation
- Sarvesh: BX + WX UI automation
- Prachi: Communication UI + cross-browser testing
- GD: UI framework utilities and responsive testing
Week 9 Activities (Mar 10-16, 2025):
- All Team: Secondary module completion and cross-browser validation
Phase 4: Integration & Deployment (Weeks 10-12)
Week 10-11 Activities (Mar 17-30, 2025):
- All Team: End-to-end scenarios and cross-module integration
- Sarvesh: CI/CD pipeline implementation
- GD: Performance testing execution
Week 12 Activities (Mar 31 - Apr 6, 2025):
- All Team: CI/CD optimization and documentation
- Prachi: Knowledge transfer materials
- Hetal: Project closure and maintenance handover
2.2 Communication
Internal Team Communication:
Daily Standups (9:00 AM):
- 15-minute focused updates
- Blockers and dependencies identification
- Daily goal alignment
Weekly Team Retrospectives (Fridays 2:00 PM):
- Process improvement discussions
- Technical challenge resolution
- Knowledge sharing sessions
Technical Deep Dives (As needed):
- Architecture decisions
- Complex implementation discussions
- Framework optimization sessions
Project Communication Channels:
Primary Communication:
- Project Slack Channel: Real-time updates and quick discussions
- Email Updates: Formal status reports and milestone communications
- Confluence/Wiki: Documentation and knowledge base
Documentation Protocol:
- Daily: Progress updates in project tracking tool
- Weekly: Status reports for stakeholder communication
- Phase Gates: Comprehensive milestone reports
Cross-team Coordination:
- Development Teams: API availability and environment coordination
- DevOps Team: CI/CD pipeline setup and deployment procedures
- Business Teams: Requirements clarification and UAT coordination
2.3 Resources and Constraints
Current Team Resources:
- Hetal: Senior Automation Engineer (Lead) - Full allocation
- Sarvesh: Automation Engineer - Full allocation
- Jay: Automation Engineer - Full allocation
- GD: Automation Engineer - Full allocation
- Prachi: Automation Engineer - Full allocation
Resource Requirements and Constraints:
Infrastructure Dependencies:
- Pre-production environment stability (Critical Week 1)
- API documentation completeness (Critical Week 2)
- Development environment access for all team members
Potential Resource Additions:
- Week 4-6: Additional API testing support if CX-Web complexity exceeds estimates
- Week 7-9: UI automation specialist for complex web components
- Week 10-12: DevOps engineer support for CI/CD optimization
Training and Skill Development:
- Playwright framework training (Week 3)
- CI/CD tools training (Week 11)
- Knowledge transfer sessions (Week 12)
Risk Mitigation - Resource Planning:
Backup Resource Strategy:
- Cross-training between team members for knowledge redundancy
- Contractor/consultant identification for critical skill gaps
- Escalation to management for additional resources if timeline at risk
Capacity Management:
- 80% utilization target to allow for unexpected challenges
- Buffer time built into critical phases
- Scope adjustment procedures for resource constraints
Success Metrics:
- Coverage: 95% API automation, 85% UI automation by Week 12
- Quality: >98% test reliability in pre-production
- Performance: <4 hours full regression suite execution
- Team Effectiveness: 100% knowledge transfer completion by Week 12